01
Pool structure
Excavation, steel, gunite, plumbing and backfill for the pool and sunshelf.
Excavation and dirt removal
Dig the 14' x 34' pool and sunshelf, 3' to 6' deep, and haul the dirt off site.
See details
Pool Excavation & Dirt Removal · 100 Linear Feet × $50
- Pool shell excavation and haul-off/removal of excavated dirt from the job site. Priced per linear foot.
Rebar and forms
Forms around the perimeter and a full engineered steel grid, bonded per NEC 680 and inspected before gunite.
See details
Rebar & Forms · 100 Linear Feet × $50
- Layout and setting of forms around the pool perimeter to establish the shell shape and beam
- Supply and installation of steel rebar per engineered spacing and size, tied in a grid across the floor, walls, steps, benches and beam
- Rebar supports/chairs to hold proper clearance for the gunite
- Bonding of the steel per NEC 680 requirements (bonding inspection coordinated per permit)
- Steel inspection coordinated before gunite
Gunite shell
Shotcrete shell for the pool, steps and sunshelf, built to the engineer's plans and the Florida Building Code.
See details
Gunite · 100 Linear Feet × $185
- Gunite (shotcrete) application for the pool shell, built to the structural engineer's plans and Florida Building Code.
Perimeter piping and rough plumbing
Main drain, skimmers, returns and feature lines to the equipment pad, pressure tested twice and inspected.
See details
Perimeter Piping & Rough Plumbing · 1 Each × $4,500
- Before gunite: main drain lines installed and pressure tested
- After gunite and first backfill: trenching for the plumbing runs to the equipment pad
- PVC piping and fittings for skimmers, returns and suction lines
- Rough-in of lines for the pool features shown on the plans
- Second pressure test and inspection before the second backfill
- Final equipment connections at the pad not included unless noted
Backfill and grading to deck level
Two-stage backfill and compaction, graded to deck level with slope away from the pool and the house.
See details
Backfill & Grading To Deck Level · 1 Each × $3,200
- First backfill around the shell after gunite and form removal
- Second backfill in compacted lifts after the piping and electrical inspection
- Grading to the deck sub-grade with slope away from the pool and house
- Final leveling and cleanup of excess material
- Import of additional fill not included unless noted